EMPLOYER NAME CONTRACT DATE COMPLETION DATE CONTRACT VALUE (TL) FINAL ESTIMATION SUM ($)
Ministry Of Public Works General Directorate Of Highways, Highways 15 th Regional Directorate
KASTAMONU
Çaycuma - Perşembe - Bartın Road
(Between Çaycuma - Perşembe)
Leveling Art Structures And Upper Structures Works
KASTAMONU
19/01/1998 21/11/05 183.294.21 TL
(1997 B.F)
277.287.29 TL
1.295.075 $
İller Bank General Directorate ACIGÖL (Nevşehir) Sewerage Construction Works 23/03/00 13/01/05 1.039.350.00 TL
(1999 B.F)
978.182.86 TL
1.663.407 $
AKTÜRK Construction Industry and Trade Co. Inc AŞTİ Çayyolu 1 st Stage Rail System Lines Construction and Building Works
(Excavation Reinforcement Works)
18/11/02 19/01/04 800.000 $ 633.925 $
Ankara Water and Sewerage Administration General Directorate Channel Investment Department Ankara- Kazan Road Between Demetevler Crossroad - Highway Croosroad
KM: 3+969 - 21+437
Road Expansion, Rain Water, Waste Water Sewerage And Portable Water System Construction Works
23/01/03 01/08/04 23.560.000.00 TL
(2002 B.F)
41.087.164.86 TL
25.019.312 $
Ministry of Resettlement And Public Works Structural Works General Directorate Ankara Güvercinlik Gendarmarie Military Equipment Main Repair Factory Command, Workshop Building Construction Works 12/12/01
Söz. Dev. Tar.
13/05/03
30/12/04 2.183.000.00 TL
(2001 B.F)
2.052.000.000 TL
1.425.428 $
Ministry Of Public Works General Directorate Of Highways, Highways 15 th Regional Directorate
KASTAMONU
Çaycuma - Perşembe - Bartın Road
KM: 0+000 - 10+000
Leveling Art Structures And Upper Structures Works
04/11/03 20/12/04 976.173.75 TL
(2003 B.F)
960.184.03 TL
649.251 $
Ministry Of Public Works General Directorate Of Highways, Highways 2nd Regional Directorate
İZMİR
Aliağa - Ayvalık 14 th Region Hd. Road
KM: 80+000 - 101+000
Leveling Art Structures And Upper Structures Works
İZMİR
11/02/04 10/05/05 3.705.078.25 TL
(2003 B.F)
3.866.013.10 TL
2.614.094 $
TCDD General Directorate
( OHL - ALSİM ALARKO - GYO Joint Venture )
Rehabilitation Project Of Ankara - Istanbul Railway. Earthworks 1 Btw.
KM: 353+000 - 375+000
KM: 375+000 - 388+000
Art Structures, Embankment Works Between
KM: 375+400 - 388+000
14/05/04 14/07/04 2.889.080 € 2.889.080 €
Ankara Water and Sewerage Administration General Directorate Channel Investment Department 1011 Bridge Cross Road And Substructure Replacement Construction Works 16/05/05 21/06/06 15.336.386.24 TL 16.855.596.06 TL
12.249.706 $
YDA Construction Industry And Trade Co. Inc. Concasor And Mechanic Plant Operating And Transportation of Material To The Employer Site For Dalaman Air Port New Outer Lines Terminal Building And Other Related Structures 23/11/04 23/05/05 6.675.000.00 TL
(2004 B.F)
6.675.000.00 TL
4.634.567 $
Capital City Organized Industrial Region
(SİTİYAK)
Capital City OSB Completion Of Excavation And Filling Works 20/05/04 14/10/04 875.000.00 TL
(2004 B.F)
875.000.00 TL
564.623 $
Ankara Water and Sewerage Administration General Directorate Channel Investment Department Ankara - Istanbul Road 2 nd Group 7 Units Pedestrian Top Passing Steel Construction 01/06/05 03/12/05 2.940.000.00 TL
(2005 B.F)
2.582.631.00 TL
1.899.691 $
Ankara Water and Sewerage Administration General Directorate Channel Investment Department 1011 Crossroad 3 Units Pedestrian Top Passing Steel Construction 22/08/05 29/01/06 1.175.000.00 TL
(2005 B.F)
1.136.225.00 TL
834.723 $
Ankara Water and Sewerage Administration General Directorate Channel Investment Department Ankara Big City Municipality Various Region Street And Road Sewerage And Rainwater Project And Substructure Sewerage Construction 17/10/05 26/06/07 44.484.764.45 TL
53.351.688.62 TL
39.385.566.67 $
Ankara Water and Sewerage Administration Water Construction Department Mounting, Laying and Cathodic Protection of the Steel Pipe To Be Supplied for the Main Transmission Line to Deliver Water from Kesikköprü Dam to Ankara Ivedik Treatment Plants 11/05/07 15/12/07 23.250.500.00 TL 77.104.107.98 TL
57.527.557.20 $
ETİ Maden Operation General Directorate Bigadiç Boron Operation Directorate
BALIKESİR
Bigadiç Boron Operation Directorate Measured Weighted Steel Yard Simav Open Quarry With 42.000.000 Tones Capacity Decoupage Work 03/02/06 21/02/08 50.400.000.00 TL 50.400.000.00 TL
38.202.076 $